General Construction Update


Tower Crane Erection

  • The next tower crane is scheduled to be installed and commissioned on 15 and 16 March, taking the total number of cranes at Barangaroo South to 10.

Stormwater Diversion Works

  • The final phases if stormwater works continue in Hickson Road and are scheduled to be completed by Saturday 15 March.

 