MAY 2020 CONSTRUCTION UPDATE


The latest construction update and look ahead for the Walsh Bay Arts Precinct project is available,  to see the latest update from INSW. Click here

Construction Update – Pier 2/3
  • The concrete stairs on the eastern side have been demolished. Works are on track to rebuild the new stairs. 
  • Structural timber rectification works have commenced and are proceeding well. 
  • Installation of structural steel has commenced.

Construction Update – Wharf 4/5 

  • Rectification to the wharf sub-structure has been ongoing. 
  • Construction of the internal spaces in each of the tenancy areas is taking shape. Services installations have also been ongoing in all tenancy areas. 
  • The old solar panels have been removed and the existing roof sheeting is being inspected before the new state-of-the-art photovoltaic solar system is installed.
 Upcoming work expected over the next month:
  • Continuing to rebuild the concrete stairs on the eastern side of Pier 2/3.
  • Erecting scaffolding on the external Pier 2/3 facades. 
  • Continuing the timber rectification works and structural steel installations at Pier 2/3. 
  • Commencing works to lift portions of the roof in at Pier 2/3. 
  • Continuing with the rectification for the Wharf 4/5 sub-structure, including erection of temporary steel bracing on the western apron. 
  • Commencing balcony rectification works on the western façade of Wharf 4/5. 
  • Continuing with roof works on Wharf 4/5 before installing new solar panels.

       Click here to visit the official website         

                                                          
 
 

Despite some wet weather this week, our Barangaroo team made further progress deep underground where concreting activities are ongoing to build the permanent station structure. Work is also continuing by the foreshore to remove the concrete hardstand area where the spoil shed and tunnelling support infrastructure were located. These activities will continue in the coming weeks.

Out-of-hours work next week

Work will continue 24/7 next week to install waterproof lining and pour concrete in the underground crossover cavern and new Barangaroo Station. Work will involve the use of hand tools, concrete trucks, loaders, elevated working platforms, pumps and cranes. This work is not expected to cause high noise at nearby properties.

Community enquiries

If you have any questions, please contact our team on 1800 171 386 or at This email address is being protected from spambots. You need JavaScript enabled to view it.. Alternatively, you can visit the Sydney Metro website to view all current and past construction updates.


Mark
Community Place Manager | Barangaroo & Blues Point
John Holland CPB Ghella (JHCPBG)
 
 
A Special Thanks
to Chris from
Walsh Bay Wine Cellar 


Chris donated 160 desk size hand sanitisers to be distributed to our local cafes and restaurants

Thanks Chris!! donation received well. 



 
 
Facebook
Website
 

Walsh Bay Newsletter Sign Up